MWBE Reporting on Federally Funded Projects: What You Need to Track

MWBE / MWSBE5 min readNovember 2024

MWBE Reporting on Federally Funded Projects: What You Need to Track

Minority and women-owned business enterprise reporting is a requirement on many federally funded and HUD-assisted construction projects. Here's what to track, how to document it, and how to meet your contracting goals.

SR

Stephanie Ramirez

CEO & Founder, S&R Industrial Contract Consulting

What MWBE Reporting Requires

Minority and Women-owned Business Enterprise (MWBE) reporting — also referred to as MWSBE, DBE, or Section 3 business reporting depending on the funding agency — requires contractors to document the participation of certified minority-owned, women-owned, and small business enterprises in the project's subcontracting and procurement activity.

The specific requirements vary by funding agency. HUD-assisted projects typically require tracking of Section 3 businesses alongside MWBE firms. Texas GLO and TDHCA projects have their own MWBE participation goals and documentation requirements. City of Houston projects require reporting through B2Gnow. Confirm the specific requirements with your funding agency before the project begins.

What to Track at the Subcontractor Level

For each subcontractor and supplier on the project, you need to track: the firm's certification status (MBE, WBE, DBE, Section 3 business, or none), the contract amount awarded to that firm, the actual dollars paid to that firm at each pay period, and the percentage of total contract value represented by certified firms.

Certification must be verified at the time of subcontract award — not at closeout. A subcontractor that claims MBE status but is not certified with the relevant certifying body does not count toward your MWBE goals. Obtain copies of current certifications before executing subcontracts.

Documentation That Protects You in an Audit

The documentation that matters most in an MWBE audit is evidence of your outreach efforts before subcontract award. This includes solicitation records showing that certified firms were contacted and given a genuine opportunity to bid, bid tabulations showing the prices received from certified and non-certified firms, and written explanations for any cases where a certified firm's bid was not accepted.

Post-award documentation — subcontract agreements, payment records, and utilization reports — is also required, but outreach documentation is what demonstrates good-faith effort when participation goals are not fully met.

Reporting Frequency and Platform Requirements

MWBE reporting frequency varies by project. Some funding agencies require monthly reports; others require updates at each pay application. City of Houston projects using B2Gnow require that subcontractor payments be logged in the platform within a specified number of days of each payment.

Do not wait until the end of the project to compile MWBE data. Establish a routine of updating your utilization tracking at each pay period, and reconcile your records against actual payment data before each submission. Discrepancies between reported and actual payments are a common audit finding.

When You Cannot Meet Your MWBE Goals

If market conditions, trade availability, or project scope make it impossible to meet your MWBE participation goals, document your good-faith efforts thoroughly and notify the funding agency proactively. Most agencies have a process for reviewing and approving good-faith effort documentation when goals cannot be met.

The worst outcome in an MWBE audit is not failing to meet a goal — it is failing to document that you tried. A well-documented good-faith effort, submitted proactively, is almost always treated more favorably than a deficiency discovered during a post-project audit.

Need Help With Compliance on Your Project?

S&R provides hands-on federal labor compliance support for developers and general contractors on HUD, GLO, TDHCA, and City-funded projects.